This meeting is scheduled primarily to recap issues and responses to the major winter (heavy wet snow) storm in December 2014. It will also provide an opportunity for emergency response personnel to discuss preparation for closing “Truchon” bridge on East River Road July – August 2015. PLEASE NOTE: A Public Information Meeting regarding the bridge closure is scheduled for Tue May 26 @ 7:00 PM  at Burnham Hall.

Special Select Board Meeting 05.12.15

SB Agenda 05.12.15

Select Board Meeting 05.05.15 Agenda

1. SB Agenda 05.04.15

Select Board Agenda 04.30.15

1. SB Agenda 04.30.15 Re-Sched

LINCOLN TOWN OFFICE PROJECT UPDATE

LINCOLN TOWN OFFICE PROJECT UPDATE

PROGRESS

  • Construction bids will be received on April 30
  • State water and wastewater permits – approved
  • Boundary adjustment and septic easement drafted for signature
  • VMBB or commercial bank financing will be decided in May
  • Construction start anticipated in summer 2015

DETAILS

We are happy to report that our Town Office addition and renovation project approved by voters at March Town meeting continues to make good progress. Bid documents were delivered to three qualified contractors on April 3. We were disappointed that one of the contractors has declined to bid citing his success in winning three substantial contracts in one week. We met with the two remaining contractors on April 10 and are looking forward to their bid submissions on April 30. Each contractor is required to assemble a professional team of architects, engineers and tradesfolk to assure that the Town gets the best possible value while fully complying with a myriad of permits and regulations.

We are pleased to have received state water and wastewater permits for the project. The permit applications, site planning and system design were completed by Lincoln Applied Geology and required generous cooperation of the Town’s neighboring property owners, Weathervane United, Inc. and the Lincoln Historical Society. A minor boundary line adjustment with Weathervane will enable the new addition to meet all set back requirements. An easement from the Lincoln Historical Society will facilitate construction of a septic mound system. In exchange for the easement, the Historical Society will gain controlled access to the new restroom and conference rooms in the new Town office. A separate agreement will provide some space in the new Town vault for the Historical Society to securely house some delicate, irreplaceable documents.

The Select Board is preparing to make final arrangements for project financing before the middle of May. The Town has proposed to finance the project through the services of the Vermont Bond Bank. Since Town Meeting we have been approached by a Vermont bank offering financing at very competitive interest rates for the same twenty year term. The bank financing would be structured much like a residential mortgage with equal annual payments comprised largely of interest in the early years with principal payments increasing annually. The VMBB payments are structured so that principal is paid in equal amounts for each of the twenty years while the interest rate varies depending on the performance of the bond market. The end result in total principal repaid and interest paid is virtually identical. The main advantage to the bank financing appears to be significantly reduced application and administrative requirements. No matter which financing vehicle is chosen. The total annual payments made by the Town will fall well within the current taxes collected to fund the capital plan.

Assuming all goes well with the bids received and construction contract negotiation is successful, ground will be broken, hopefully this summer.

Once again we extend our thanks to this community for support of this important project. We are confident that Lincoln will be graced by an appealing building that will serve the Town’s needs well for many years to come.

03.17.15 Select Board Meeting Re-Scheduled to 03.24.15

The Select Board Meeting regularly scheduled for 3/17/15 has been re-scheduled to 3/24/15. Agenda will be posted prior to the meeting.