PUBLIC INFORMATION MEETING – 05.26.15 re: TH 1 Bridge 19 “Truchon Bridge” EAST RIVER ROAD CLOSING
“Truchon Bridge” on East River Road will be replaced this summer. East River Road will be totally closed to through traffic for a single period of up to 50 days between mid-June and late August. The estimated start of full closure is July 2. By closing the road entirely, the construction schedule is shortened substantially and the Town’s share of the nearly $2.4 million project, funded by property taxes, is reduced by 50%. This public Information meeting will be an opportunity to learn and to ask questions about the schedule and plans.